Click on any project to see the complete details
Beta Engineering Corporation
- SDG&E Suncrest Substation – 500 kV/230 kV Substation Construction
-
Constructed a new 500/230kV substation, including erecting and installing steel structures for two 500kV positions with operating buses, two transformer banks and one spare position, 13.8kV tertiary buses and associated shunt reactor banks, and two 230kV positions with operating buses. In addition, NRG installed circuit breakers, disconnects, emergency generators, 230kV capacitor banks, and other electrical equipment. Our team installed relay racks and an AC/DC system in control shelter, and pulled and terminated secondary power and control cables. We began electrical construction for this project in August 2011 and finished in April 2012.
View a photo gallery of this project - SCE Lugo Substation – 500kV Capacitor Banks Installation
- NRG installed 500kV series capacitor banks, erected and installed new steel structures and platforms. Our team also installed 500kV capacitor racks and other associated work including MEER Building, MOVs, spark-gaps, and state of the art circuit switchers. We completed the installation of the two double capacitor banks between June and December 2010.
- SCE Devers Substation – Static VAR Compensator Installation
- Our NRG team installed one 500kV MSC Capacitor bank including steel towers, circuit breaker, ground disconnect, PT’s, capacitor racks, reactor, miscellaneous electrical equipment and buses. In addition, we installed a 13.7kV Shunt VAR Compensator system with TRC, TSC and Filter yards – including 12,000 Amp rigid main bus, motor operated disconnects, reactors, capacitor racks, lighting arresters, PT’s and CT’s. We also installed thyrister valves and associated cooling system, as well as relay racks, control panels, RTU, Marshall Panels and associated power and control cables. Our work on this project in May 2006 and we finished it by September of 2006.
- SCE Vincent Substation – 500kV Capacitor Banks Replacement
- The NRG team demolished the existing steel structure and 500kV capacitor banks at the Vincent Substation, and erected and installed new steel structures and platforms. We also installed 500kV capacitor banks and other associated work including MEER Building, MOVs, thyristers, and state of the art circuit switchers. Our team replaced four capacitor banks at this location between December 1999 and May 2004.
Mitsubishi Electric Power Products, Inc.
- SCE Rancho Vista Substation – 550kV and 245kV GIS Installation
-
At this comprehensive project, our NRG team installed new Mitsubishi 550kV and 245kV gas insulated equipment and CGIT buses with associated support structures and air to gas bushings. In addition, we installed walkways and platforms, gas manifolds and monitors, cable trays and local control cabinets, and secondary wiring. Furthermore, after the completion of the GIS installation, we assisted SCE with the installation of primary conductorings where needed, transformer firewalls, yard lighting, and other miscellaneous work. Our team performed this complex project between March 2008 and June 2009.
View a photo gallery of this project - SCE Lugo and Devers Substations – 550kV GIS Circuit Breakers Installation
- NRG replaced existing 550kV circuit breakers with new Mitsubishi gas insulated breakers. Our work included removing old equipment and installing new devices along with primary and secondary cables. We started this project in September 2005 and completed it in December 2005.
- SCE Rector Substation – Static VAR Compensator Installation
- NRG installed a 13.7kV Shunt VAR Compensator system with TRC, TSC and Filter yards – including 10” IPS main bus, motor operate disconnects, reactors, capacitor racks, lighting arrester, PT’s and CT’s. We also installed thyrister valves and an associated cooling system, as well as fabricated and installed relay racks, control panels, RTU, and Marshall Panels. In addition, we installed a ground bank, station light and power, and AC/DC system. This project started in January 2007 and our team completed it by May 2007.
- SCE Valley Substation – 115kV GIS Switchrack Extension
- The NRG team installed new Mitsubishi 245kV and 115kV gas insulated equipment and CGIT buses with associated support structures and air to gas bushings. We removed and modified existing platforms, conduit, junction boxes, cables, bus, supports and other equipment and material required for the new breakers installation. In addition, we installed support columns, walkways and platforms, gas manifolds and monitors, cable trays and local control cabinets, and secondary wiring. NRG performed this work during March and December 2005 and May 2006.
- SCE Serrano Substation – 550kV and 245kV GIS Replacement
- NRG deployed a 550kV and a 245kV gas insulated switchgear project. We demolished existing steel supports, platforms, and ASEA gas insulated switchgear, and installed support structures and new state-of-the-art 550kV and 245kV gas insulated circuit breakers and buses. In addition, our team installed gas manifolds and monitors, walkways and platforms, and cable trays and local control cabinets. We started the 550kV project in November 99 and completed it in June 2001. The 245kV project began in September 2001 and we completed it in June 2002.
Southern California Edison
- SCE Antelope Substation – Construction and Expansion of 500kV Switchyard
-
NRG built and expanded a new 500kV switchyard as part of Tehachapi Renewable Transmission Project. This included erecting and installing all new steel structures and supports for four new 500kV positions, two 500kV operating buses, two transformer banks and one spare position, one 500kV and one 220kV emergency jack buses, and two 13.8 tertiary buses. In addition, our team installed circuit breakers, disconnects, emergency generators, GE 500kV capacitor banks, and other electrical equipment. We also installed primary overhead cables to major electrical equipment and secondary cables to relay/control building. Our team began the electrical construction for this project in December 2010 and completed the work by November 2011.
View a photo gallery of this project - SCE Valley Substation – 500kV Switchyard Installation
- The NRG team extended operating buses, constructed two new positions, and upgraded three existing positions. We erected and installed steel structures and supports, assembled and installed circuit breakers, disconnects, and other electrical equipment, and installed primary conductor to major electrical equipment and secondary cables to relay/control building. The electrical equipment installation for this project started in January 2009 and was completed in June 2009.
- SCE Viejo Substation – New 220kV Substation Construction
- Our team built a brand new 220kV/66kV/12kV substation. This included erecting and installing all new steel structures and supports as well as setting and installing transformers, circuit breakers, and other electrical equipment. We also installed primary overhead cables to major electrical equipment and secondary cables to relays and the control building. We began the electrical equipment installation for this project in November 2004 and completed the project in June 2005.